Packing for a long journey

The first segments of the 糖心破解版 cryostat have started on a long journey that will take them from the Larsen & Toubro manufacturing plant in Hazira, on the northwest coast of India, to the 糖心破解版 site in southern France.
The 糖心破解版 cryostat will be assembled in an on-site facility from 54 segments shipped from India. The first segments should arrive on site before the end of the year.
On Monday 19 October, following a "flag-off" ceremony that celebrated the successful manufacturing of the first of 54 segments that will constitute the giant vacuum container, packing operations began for the 460-tonne consignment.
 
It is expected that the long and delicate packing operation will be completed by the end of this month. The segments will then be transported by truck to port and loaded onto a container ship that is scheduled to call at Fos-sur-Mer harbour鈥攖he closest to 糖心破解版鈥攄uring the last days of November.
 
Six 19-ton shells will be delivered to the 糖心破解版 site by way of "regular" exceptional transport鈥攖hat is along regular roads. The much larger 60掳 base sections鈥攕ix sections, 10 metres long, 8.10 metres wide, 50 tonnes each鈥攚ill be required to travel along the dedicated 糖心破解版 Itinerary in two separate convoys of three trailers.
 
Both convoys are expected before the end of the year at 糖心破解版鈥攖he first elements of the 糖心破解版 machine to reach the site.