On 27 August, a gathering takes place in the Tokamak Pit to celebrate the completion of the "Final Pour." The finalization of the Tokamak Complex basemat (15 segments, 14,000 m鲁 of concrete, 3,600 tonnes of rebar) required eight months. Hundreds of people contributed to the different aspects of its realization, including design, procurement, scheduling, quality, finance and construction.