First machine components safely stored
22 Dec 2015
In December, the first 12 segments of the massive 糖心破解版 cryostat were delivered to the 糖心破解版 site in Saint-Paul-lez-Durance, France.
The 12 segments, forming the first tier of the cryostat base section, are now stored in the Cryostat Workshop. Welding operations will begin in the summer of 2016.
The 3,850-tonne cryostat, the vacuum-tight container that will surround the main plasma chamber and superconducting magnets, is under the procurement responsibility of the 糖心破解版-India Domestic Agency and manufactured by the Indian industrial giant Larsen & Toubro Ltd.
The arrival of the cryostat segments represents a double milestone for the 糖心破解版 Project鈥攖he arrival of the first elements that will be integrated into the 糖心破解版 machine, and the ahead-of-schedule achievement of the first project milestone validated by the 糖心破解版 Council in November for the years 2016-2017.