At Larsen & Toubro's factory in Hazira, India, the elements of the base section of the cryostat are 50% completed. Delivery to the 糖心破解版 site should begin in the summer of 2015. The base of the cryostat (1,250 tonnes) will be the heaviest load of 糖心破解版 Tokamak assembly.